Vijayawada Municipal Corporation
 


Statement Showing Status of Receipts Details Under JNNRUM as on Date

Rs.in Lakhs
UIG
SNo Project Name Project Cost 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 TOTAL
Providing Water supply facilities in unserved areas.  3548  621.4  728.04  514.76  372.54  2236.74
Augumentation of Water Supply Utility Under Jnnurm Phase-II.   7231  1265.43  1525.43  1005.43  3796.29
Providing under ground drainage facilities to the unserved areas  5656  989.75  1159.51  820.09  593.93  3563.28
Providing sewerage system in Krishnalanka Area (Sector-8) of vijayawada City   743  130.02  130.02  130.02  78.01  468.07
Replacement of the existing Sewarage tratement Plant with new plant at singh nagar.  949  166.08  332.16  99.64  597.88
Providing Sewarage system in unserved areas covering Gunadala, Khuddus Nagar, Housing Board colonyand Devinagar etc.,  1985  345.78  98.85  247.13  345.88  208.93  1246.57
Storm Water Drainage System for uncovered areas in Circle I,II,III and M.G. Road.   4912  859.6  1719.2  515.76  3094.56
Providing Bus Rapid Transit system facility in vijayawada city. (BRTS)   15264  2671.2  2671.2  500  5842.4
Municipal solid waste  5805  1015.25  1109.15  2124.4
10  Restoration of Roads  3625  634.37  1014.99  1649.36
11  Providing sewerage systemin northen part of the city  17815  3117.49  1000.25  4117.74
12  Implentation of NMMP on e-Governance Project in Vijayawada City  402.76  0
  Sub Total of UIG 67935.76 2470.75 4578.51 2116.42 9593.72 4484.69 5493.2 0 28737.29
BSUP
SNo Project Name Project Cost 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 TOTAL
13  Detailed Desingn and estimations for Basic Services to Urban Poor in Circle-I area   370  64.75  129.52  64.75  259.02
14  Detailed designs and Estimations for Basic Services to Urban Poor (BSUP) Circle-II VJA.  5983  896.74  599.02  1553.86  506.07  3555.69
15  Detailed designs and Estimations for Basic Services to Urban Poor (BSUP) Circle-II & III area VJA.  2648  449.97  449.97  449.97  172.62  1522.53
16  Construction of 15,000 houses for the rehabitation of flood victims of river krishna & budemeru Vagu along with infrastructure development in VMC area  25874  4527.89  9055.78  3610.22  17193.89
17  DPR for providing G+3 Group housing and BSUP in Slums located in Circle-1 of VMC.  19088  3208.84  1334.77  4543.61
18  Repairs to Dwelling unit constructed under vambay colony  773  133.48  272.78  93.81  500.07
19  Providing housing under Phase III  9797  1714.48  1714.48
20  Providing housing under Phase IV  9798  1714.65  1714.51  3429.16
  Sub Total of BSUP 74331 0 5939.35 4520.83 11332.39 3493.88 7432 0 32718.45
  Grand Total 142266.76 2470.75 10517.86 6637.25 20926.11 7978.57 12925.2 0 61455.74
vmc