Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Municipal Solid Waste Management in Vijayawada City.  5805 
Work Description:

"Supply and delievery of 20 tons capacityhydraulic Excavator "

File No. : Rc/V1/157545/2010 Estimated Cost
(Rs. in Lakhs)
: 54.22
Circle No. : 7 Admin. Approval Dt. : 30-5-2009
Technical Sanction Dt. : 30-5-2009 Tender Dt. : 30-5-2009
Work Order Dt. : 9-4-2010 Contractor Name : M/s Varun Motors
Agreement No. : 38 Agreement Dt. : 18-6-2009
Agreement Amt.
(Rs. in Lakhs)
: 56.25 Period of Completion
(Months)
: 3
Actual Dt. of Completion : 30-6-2010

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  30-6-2010 45.28 
TOTAL 45.28 