Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Municipal Solid Waste Management in Vijayawada City.  5805 
Work Description:

Supply and delivery of 7 Tons capacity Proclainer

File No. : Rc/V1/157544/2009 Estimated Cost
(Rs. in Lakhs)
: 29.99
Circle No. : 7 Admin. Approval Dt. : 3-11-2009
Technical Sanction Dt. : 30-11-2009 Tender Dt. : 2-12-2009
Work Order Dt. : 22-1-2010 Contractor Name : M/s Varun Motors
Agreement No. : 167 Agreement Dt. : 3-2-2010
Agreement Amt.
(Rs. in Lakhs)
: 25.3 Period of Completion
(Months)
: 3
Actual Dt. of Completion : 26-3-2010

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  26-3-2010 20.87 
TOTAL 20.87 


vmc