Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Municipal Solid Waste Management in Vijayawada City.  5805 
Work Description:

Construction of 150 MT transferstation at Autonagar old DP Station.

File No. : Rc/V1/132519/2009 Estimated Cost
(Rs. in Lakhs)
: 230
Circle No. : 7 Admin. Approval Dt. : 27-6-2009
Technical Sanction Dt. : 27-6-2009 Tender Dt. : 29-6-2009
Work Order Dt. : 4-8-2009 Contractor Name : M/s APR Projects Pvt Ltd
Agreement No. : 28 Agreement Dt. : 20-8-2009
Agreement Amt.
(Rs. in Lakhs)
: 224.26 Period of Completion
(Months)
: 6
Actual Dt. of Completion : 8-5-2011

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  9-5-2011 139.75 
TOTAL 139.75 