| SubMission | Project Name | Project Cost (Rs. in Lakhs) |
||||||
| UIG | Providing Municipal Solid Waste Management in Vijayawada City. | 5805 | ||||||
| Work Description | : | "Providing CC (1:1.5:3) flooring and ceiling, Plastering to the Transfer Station Buildings in Singhnagar)" |
||||||
| File No. | : | Rc/V1/128282/2009 | Estimated Cost (Rs. in Lakhs) | : | 9.9 | |||
| Circle No. | : | 7 | Admin. Approval Dt. | : | 22-5-2009 | |||
| Technical Sanction Dt. | : | 8-6-2009 | Tender Dt. | : | 8-6-2009 | |||
| Work Order Dt. | : | 8-7-2009 | Contractor Name | : | Sri J Ravi Sankar | |||
| Agreement No. | : | 03 | Agreement Dt. | : | 21-7-2009 | |||
| Agreement Amt. (Rs. in Lakhs) | : | 8.61 | Period of Completion (Months) | : | 2 | |||
| Actual Dt. of Completion | : | 12-11-2009 | ||||||
| S No. | Physical Progress | Progress As On | Payment Made (Rs. in Lakhs) |
| 1 | WORK COMPLETED | 12-11-2009 | 7.63 |
| TOTAL | 7.63 | ||