Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Municipal Solid Waste Management in Vijayawada City.  5805 
Work Description:

"Rehabilitation of Existing Dump site at Excel Plant Location South side of Sri Ram Energy Plant opp. Vambay Colony Gate to nearest Transfer Station.

File No. : Rc/V1/128278/2009 Estimated Cost
(Rs. in Lakhs)
: 38.72
Circle No. : 7 Admin. Approval Dt. : 22-5-2009
Technical Sanction Dt. : 8-6-2009 Tender Dt. : 8-6-2009
Work Order Dt. : 8-7-2009 Contractor Name : M/s Myneni Construction & Contractor
Agreement No. : 79 Agreement Dt. : 25-8-2009
Agreement Amt.
(Rs. in Lakhs)
: 33.57 Period of Completion
(Months)
: 2
Actual Dt. of Completion : 1-9-2009

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  1-9-2009 30.32 
TOTAL 30.32 


vmc