SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Municipal Solid Waste Management in Vijayawada City.  5805 
Work Description:

Rehabilitation of Existing Dump site at Excel Plant Location on west side of Sri Ram Energy Plant from South side Transfer Station to North side Vambay colony Road.

File No. : Rc/V1/128268/2009 Estimated Cost
(Rs. in Lakhs)
: 49.5
Circle No. : 7 Admin. Approval Dt. : 8-5-2009
Technical Sanction Dt. : 8-5-2009 Tender Dt. : 30-5-2009
Work Order Dt. : 8-7-2009 Contractor Name : Sri Mulgauri Raghavendra Prasad
Agreement No. : 63 Agreement Dt. : 24-12-2009
Agreement Amt.
(Rs. in Lakhs)
: 41.48 Period of Completion
(Months)
: 2
Actual Dt. of Completion : 30-4-2011

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  30-4-2011 26.76 
TOTAL 26.76 