UIG  Providing Sewerage System in un-served areas covering Gunadala, Khuddus Nagar, Housing Board Colony, Devi Nagar etc.,  1985 
Work Description:

Laying of 1000 mm dia M.S. Pipe under Railway Track with Jacking System at Devi Nagar.

File No. : Rc/E9/157447/2010 Estimated Cost
(Rs. in Lakhs)
: 62.94
Circle No. : 4 Admin. Approval Dt. : 24-10-2009
Technical Sanction Dt. : 28-10-2028 Tender Dt. : 2-11-2009
Work Order Dt. : 19-11-2009 Contractor Name : M/S. SAI CONSTRUCTION CORPORATION
Agreement No. : CE-1/09-10 Agreement Dt. : 17-4-2010
Agreement Amt.
(Rs. in Lakhs)
: 60.31 Period of Completion
(Months)
: 3
Actual Dt. of Completion : 16-7-2010

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  16-7-2010 51.54 
TOTAL 51.54 