Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Sewerage System in un-served areas covering Gunadala, Khuddus Nagar, Housing Board Colony, Devi Nagar etc.,  1985 
Work Description:

Design, Fabrication, Supply, Delivery and erection or required capacity transformers with DP structure and all required accessories for 6 A and Kabela drainage pumping station

File No. : Rc/E9/148515/2009 Estimated Cost
(Rs. in Lakhs)
: 20.66
Circle No. : 4 Admin. Approval Dt. : 20-10-2008
Technical Sanction Dt. : 23-10-2008 Tender Dt. : 31-10-2008
Work Order Dt. : 29-11-2008 Contractor Name : M/S. MAITREYA ELECTRICAL (P) LTD
Agreement No. : SE-18/08-09 Agreement Dt. : 15-12-2008
Agreement Amt.
(Rs. in Lakhs)
: 20.08 Period of Completion
(Months)
: 3
Actual Dt. of Completion : 14-3-2009

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  30-4-2011 17.47 
TOTAL 17.47 


vmc