Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Sewerage System in un-served areas covering Gunadala, Khuddus Nagar, Housing Board Colony, Devi Nagar etc.,  1985 
Work Description:

Supply and erection of required capacity pump sets with required specials for Phase-II DP Stations with one year maintenance.

File No. : Rc/E9/147937/2008 Estimated Cost
(Rs. in Lakhs)
: 126
Circle No. : 4 Admin. Approval Dt. : 17-10-2008
Technical Sanction Dt. : 26-11-2008 Tender Dt. : 22-11-2008
Work Order Dt. : 5-1-2009 Contractor Name : M/S. SRI RAVI ENTERPRISES
Agreement No. : CE-78/08-09 Agreement Dt. : 11-2-2009
Agreement Amt.
(Rs. in Lakhs)
: 107.46 Period of Completion
(Months)
: 6
Actual Dt. of Completion : 30-4-2011

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  10-8-2009 95.96 
TOTAL 95.96 


vmc