| SubMission | Project Name | Project Cost (Rs. in Lakhs) |
||||||
| UIG | Providing Sewerage system in Krishna Lanka area (Sector-8) of Vijayawada City. | 743 | ||||||
| Work Description | : | Construction of Compound Wall to Krishna Lanka Drainage Pumping Station in Sector-7 |
||||||
| File No. | : | Rc/E9/045659/2007 | Estimated Cost (Rs. in Lakhs) | : | 5.8 | |||
| Circle No. | : | 4 | Admin. Approval Dt. | : | 18-8-2007 | |||
| Technical Sanction Dt. | : | 5-9-2007 | Tender Dt. | : | 11-9-2007 | |||
| Work Order Dt. | : | 20-9-2007 | Contractor Name | : | SRI. G.V. RAMA RAO | |||
| Agreement No. | : | EE-17/07-08 | Agreement Dt. | : | 28-9-2007 | |||
| Agreement Amt. (Rs. in Lakhs) | : | 5.21 | Period of Completion (Months) | : | 3 | |||
| Actual Dt. of Completion | : | 13-12-2007 | ||||||
| S No. | Physical Progress | Progress As On | Payment Made (Rs. in Lakhs) |
| 1 | WORK COMPLETED | 13-12-2007 | 5.1 |
| TOTAL | 5.1 | ||
| vmc | ||