Vijayawada Municipal Corporation
 


Work Details


SubMission Project Name Project Cost
(Rs. in Lakhs)
UIG  Providing Sewerage system in Krishna Lanka area (Sector-8) of Vijayawada City.  743 
Work Description:

Construction of Inlet Chamber, Screen & Grit Chamber, Sump cum Pump House in Chalasani Nagar, Sector-8

File No. : Rc/E9/025499/2007 Estimated Cost
(Rs. in Lakhs)
: 170
Circle No. : 4 Admin. Approval Dt. : 9-8-2007
Technical Sanction Dt. : 17-8-2007 Tender Dt. : 1-12-2007
Work Order Dt. : 27-12-2007 Contractor Name : SRI. V. SANJEEVA REDDY
Agreement No. : CE-63/07-08 Agreement Dt. : 2-2-2008
Agreement Amt.
(Rs. in Lakhs)
: 175.07 Period of Completion
(Months)
: 12
Actual Dt. of Completion : 20-9-2010

WORK PROGRESS AND PAYMENT DETAILS

S No. Physical Progress Progress As On Payment Made
(Rs. in Lakhs)
WORK COMPLETED  26-9-2010 151.15 
TOTAL 151.15 


vmc